Production n Operations 4

Select The Blank
Question The design of any layout is governed by large number of factors and the best layout is expected to ________ all these factors.
Correct Answer Optimise
Your Answer Optimise


True/False
Question In case of X bar-R charts,it is ensured that the assignable causes are detected before the tolerances are violated, upper and lower statistical limits are worked out and inserted into a chart.
Correct Answer True
Your Answer True


Multiple Choice Multiple Answer
Question Expediting function is concerned with following activities
Correct Answer Communicating possible delays in delivery date commitment to sales department , Devising cures to keep rate of production in line with schedule , Progress chasing to identify delays which may hold up production
Your Answer Recording progress of work , Progress chasing to identify delays which may hold up production , Devising cures to keep rate of production in line with schedule


Multiple Choice Multiple Answer
Question Scale model used for layout analysis have following advantages
Correct Answer Nontechnical person finds it easy to comprehend , Ovehead facilities can be shown , Models can be shifted easily
Your Answer Nontechnical person finds it easy to comprehend , Ovehead facilities can be shown , Models can be shifted easily


Multiple Choice Multiple Answer
Question Which features should be covered by the specifications of materials while defining the qualitative requirement?
Correct Answer Material composition , Dimensions , Any heat treatment if required
Your Answer Material composition , Dimensions , Any heat treatment if required


Multiple Choice Single Answer
Question Technique which can help an organization to reduce inventory is called
Correct Answer MRP
Your Answer MRP


Multiple Choice Single Answer
Question How does the control chart of statistical quality control helps the operating personnel?
Correct Answer Identify the presence of an assignable cause before it develops
Your Answer Identify the presence of an assignable cause before it develops


True/False
Question Dispatching function is not a part of Production Planning
Correct Answer True
Your Answer False


Multiple Choice Multiple Answer
Question Components of Production Management include
Correct Answer Capacity Planning , Job Design , Production Planning
Your Answer Capacity Planning , Job Design , Production Planning


Multiple Choice Single Answer
Question Plant location decisions concern following type of organizations
Correct Answer Manufacturing and service organizations
Your Answer Manufacturing and service organizations


Multiple Choice Single Answer
Question Where does the central line is located in case of p-chart?
Correct Answer at p bar
Your Answer at p bar


Multiple Choice Multiple Answer
Question Which of the following are the basic requirements of quality standard?
Correct Answer Deifinite , Undesrstandable , Economically viable
Your Answer Deifinite , Undesrstandable , Economically viable


True/False
Question Independent float either affects the float of preceding activities or that of succeeding activities.
Correct Answer False
Your Answer True


Multiple Choice Multiple Answer
Question Which of the following are activities of corrective maintenance?
Correct Answer Modifications and improvements , Overhauling , Emergency repairs
Your Answer Overhauling , Lubrication as per schedule , Emergency repairs


Multiple Choice Multiple Answer
Question Which of the following observations are expected from the preventive maintenance person?
Correct Answer Wrong allignments , Overheating defects , Excessive play
Your Answer Wrong allignments , Overheating defects , Excessive play


Multiple Choice Single Answer
Question When should operator or supervisor is supposed to sign the perforated route sheet?
Correct Answer After completion of operation
Your Answer At the start of the operation


Select The Blank
Question The most commonly used methods employed to determine the critical path in case of large networks are forward pass computation and ________.
Correct Answer Backward path computation
Your Answer Critical path computation


True/False
Question The event numbers as far as possible reflect the logical relationships of the activities.
Correct Answer True
Your Answer True


Multiple Choice Multiple Answer
Question Which are the subfactors of community facilities or social infrastructure?
Correct Answer Accomodation , Educational , Entertainment
Your Answer Educational , Entertainment , Accomodation


Match The Following
Question Correct Answer Your Answer
Scheduling of interrelated activities of small projects with consideration of uncertainty of duration of activities. Critical Path Analysis Critical Path Analysis
Two machines & processing time depends on sequence of job loading Johnson's Two Machine Algorithm Johnson's Two Machine Algorithm
Sufficient orders and resonable choice of machines Index Method Index Method
Time relationship between when a product is required and when it can be made available Critical Ratio Scheduling Critical Ratio Scheduling


Select The Blank
Question Duration of each activity is referred to as ________.
Correct Answer Activity time
Your Answer Activity time


Multiple Choice Multiple Answer
Question Which of the following are examples of pure materials?
Correct Answer Bakeries , Ice factories , Woolen
Your Answer Bakeries , Ice factories , Woolen


True/False
Question Maintenance function must be decentralised apart from a size of a manufacturing organisation for it's better functioning.
Correct Answer False
Your Answer True


True/False
Question The operator should not stop production if first piece is not approved by the inspector.
Correct Answer False
Your Answer False


Multiple Choice Single Answer
Question Which of the following policies is advisable in case of low product variety and large volumes?
Correct Answer Low Skilled Labour & Special Purpose Machines
Your Answer Low Skilled Labour & Special Purpose Machines


True/False
Question Cent percent inspection does not mean inspection of component for 100% quality characteristics.
Correct Answer True
Your Answer True


Multiple Choice Single Answer
Question What do you mean by design modifications made to reduce time and effort required in carrying out maintenance work ?
Correct Answer Design-in Maintenance
Your Answer Design-in Maintenance


Multiple Choice Multiple Answer
Question Which of the following are examples of incentives offered by the Central and State Governments for setting up industries in particular locations?
Correct Answer Exemption from excise duty , Soft loans , Subsidy in electrical charges
Your Answer Exemption from excise duty , Soft loans , Subsidy in electrical charges


Select The Blank
Question The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________.
Correct Answer Overtime working
Your Answer Overtime working


True/False
Question Objective of Work Study is to improve Productivity
Correct Answer True
Your Answer True


Multiple Choice Single Answer
Question Plant Layout decisions are considered to be
Correct Answer Strategic
Your Answer Strategic


Multiple Choice Single Answer
Question What do you mean by the project duration for which the total cost is minimum?
Correct Answer Optimum duration
Your Answer Optimum duration


Select The Blank
Question A ________ helps to determine the time required by the operator to complete a specified task for the defined method at the defined pace of performance.
Correct Answer Work measurement
Your Answer Work measurement


Select The Blank
Question An Ideal OC curve is ________ shaped curve that accpets all the lots with quality equal to or better than AQL .
Correct Answer Rectangular
Your Answer Rectangular


True/False
Question Inspection order is must even for simple jobs which can be inspected by shop inspector with the tooling available on shop.
Correct Answer False
Your Answer False


Select The Blank
Question Function concerned with fixation of time allowed to qualified worker for a job is called ________.
Correct Answer Work Measurement
Your Answer Time Measurement


True/False
Question In case of X bar-R charts,it is ensured that the assignable causes are detected before the tolerances are violated, upper and lower statistical limits are worked out and inserted into a chart.
Correct Answer True
Your Answer True


Multiple Choice Single Answer
Question What is the reason of fluctuations, if the control chart evaluates that the process is not in a state of statistical control?
Correct Answer Assignable variability
Your Answer Random variability


Multiple Choice Multiple Answer
Question Which are different ways to show critical path in a network?
Correct Answer Thick Line , Red Line , Double Line
Your Answer Thick Line , Red Line , Double Line

Comments